- Turnaround Planning
   - Turnaround Checklist
      - Ignition Systems
      - Pilots
      - Flares
      - Vessels
      - Stack Inspection
      - Flare Accessories
   - Combustion Surveys
   - Turnkey Services
- Emergency Shutdown
- Upgrades and Retrofits
- Maintenance & Troubleshooting
- Literature
- Flare School
- Flare P&S Inquiry
- Flares
Burner P&S
Thermal Oxidation P&S
Vapor Control P&S

 

 

Inside John Zink:
About John Zink
Environmental, Health and Safety
COOL Technologies
Inquiries
Markets We Serve
John Zink Products:
- Burners
- Flares
- Flare Gas Recovery
- Vapor Control
- Thermal Oxidation
Parts & Service
Rentals
Sales Offices
Technology/R&D
John Zink Institute
Virtual Tour
Ignition Systems Pilots Flares Vessels Stack Inspection Flare Accessories
Utility Steam Steamizer Air Assisted Enclosed Ground

Steam Flare (EEF-QS)


Steam Flare (EEF-QS)

Shutdown Items

1.0 Check purge system. (Refer to Purge Reduction checklists.)
2.0 Remove and check pilots. (Refer to EEP checklist.)
3.0 Inspect upper steam ring.
  3.1 Check all welds for cracking.
  3.2 Check and clean steam holes.
  3.3 Check brackets for integrity.
  3.4 Remove and replace any pins or bolts connecting the ring to the brackets. (All are 310 SS.)
4.0 Inspect center steam nozzle.
  4.1 Check welds and drilling on center steam nozzle.
  4.2 Repair or replace if casting is cracked.
  4.3 Replace if holes show any indication of erosion.
5.0 Inspect steam connections.
  5.1 Replace steam flange gaskets, if necessary.
  5.2 Check flange bolts for proper torque.
6.0 Inspect body of flare tip.
  6.1 Check all welds for cracking.
  6.2 Check for visible deformation of cylinder.
  6.3 Check flame-retention ring segments. Replace any worn or missing segments.
  6.4 Check flange bolts for proper torque.
7.0 Check FFG. (Refer to Ignition checklists.)

Periodic On-line Items

1.0 Check purge system. (Refer to Purge Reduction checklists.)
2.0 Check pilots. (Refer to EEP checklist.)
3.0 Check FFG. (Refer to Ignition checklists.)

Contact a Zink® representative for more turnaround details.

Western Hemisphere Europe Asia-Pacific
1-800-755-4252
(in U.S. & Canada)
+1-918-234-2751
(International)
+352-51899-332 +65-6732-7555

John Zink Company, LLC
11920 East Apache
Tulsa, OK 74116
United States of America
+1-918-234-1800

email: info@johnzink.com